Caltrans Logo

Plaza Drive Interchange/Auxiliary Lanes

Description: In Visalia, on Route 198 from Route 99 to Plaza Drive, and on Plaza Drive from Airport Drive to Goshen Avenue. Construct auxiliary lanes (Route 198) and widen roadway (Plaza Drive).

  • Project Information
  • Contacts
  • Cost by Fund Source
  • Cost by Component
  • Schedule
  • Map
  • Closeout Info
Project Location
County
Tulare
City Visalia
Zip Code
 
Senate District
18
Assembly District 34
Congressional District 22
 
Caltrans District
06
 
 
County/State Route Tulare 198
Postmile Begin/End 4.1 5
Project Benefits
 Benefit Baseline Actual
Daily Travel Time Savings (hours)  607.7    709.6  
Lane Miles Added (HOV)      0  
Lane Miles Added (Mixed)      <2  
Peak Period Time Savings (minutes)  7259    8,476  
 
Project Contacts Agency Contact Person Telephone E-mail
Environmental Phase
City of Visalia Fred Lampe (559)713-4270   fred.lampe@visalia.city
Design (PS&E) Phase
City of Visalia Fred Lampe (559)713-4270   fred.lampe@visalia.city
Right of Way Phase
City of Visalia Fred Lampe (559)713-4270   fred.lampe@visalia.city
Construction Phase
 
 
Corridor System Management Plan
 
Project Cost Baseline Summary (Dollars Shown are in Thousands) 2
  Adopted Program
(06/07/07)
a
Approved Changes
(12/31/2023
b=c-a
Current Approved
(12/31/2023
c
Bond Funding
RIP Augmentation
$0 $0 $0
CMIA
$7,876 $13,311 $21,187
LSR
$0 $100 $100
Non-bond Funding
State/Federal*
$17,321 $-16,020 $1,301
Local**
$4,678 $0 $4,678
Non Budgeted ETC
$0 $0 $0
 
Total**** $29,875 $-2,609 $27,266

**** Totals may not add up exactly to column amounts due to rounding

# Approved is planned budget

Project Cost Baseline Summary (Dollars Shown are in Thousands)
  Adopted Program
(06/07/07)
a
Approved Changes
(12/31/2023
b=c-a
Current Approved
(12/31/2023
c
Cost to Date**
(12/31/2023
d
 
Environmental
$1,255 $0 $1,255 $1,255
Design(PS&E)
$1,924 $0 $1,924 $1,924
Right of Way
$2,900 $0 $2,900 $1,836
Construction
$23,796 $-2,609 $21,187 $22,737
 
Total* $29,875 $-2,609 $27,266 $27,752

* Totals may not add up exactly to column amounts due to rounding

** Totals include all actual project funds expenditures. Cost to date expenditure variances are explained in quarterly reports and/or Close-out reports.

Project Schedule Baseline Summary
(Schedule Changes and Variances in Months) Adopted Program
(06/07/07)
a
Approved Changes
(mm/dd/yyyy)
b
Current Approved
(12/31/2023)
c
% Complete
(12/31/2023)
d
Schedule Forecast
(12/31/2023)
e
Schedule Variance
(months)
f=c-e
Begin Environmental Phase

End Environmental Phase
07/01/1999 

10/30/2006 
 

 
07/01/1999 

10/30/2006 
100  07/01/1999 

10/30/2006 


Begin Design (PS&E) Phase

End Design (PS&E) Phase
01/15/2010 

06/10/2011 
 

 
01/15/2010 

06/10/2011 
100  01/15/2010 

06/10/2011 


Begin Right of Way Phase

End Right of Way Phase
09/01/2009 

06/10/2011 
 

 
09/01/2009 

06/10/2011 
100  09/01/2009 

06/07/2011 


Begin Construction Phase

End Construction Phase
11/30/2011 

06/30/2013 
 

 
11/30/2011 

06/30/2013 
100  11/30/2011 

08/19/2014 


-14 
Begin Closeout Phase

End Closeout Phase
07/01/2013 

12/31/2013 
 

 
07/01/2013 

12/31/2013 
100  08/19/2014 

02/01/2019 
-14 

-62 
Corridor System Management Plan
Adoption Date     09/03/2008  09/03/2008 
Implementation Date     10/03/2008  10/03/2008 
????????

No map available at this time.

Project Benefits
Benefit Baseline Actual
Daily Travel Time Savings (hours) 607.7 709.6
Lane Miles Added (HOV) 0
Lane Miles Added (Mixed) <2
Peak Period Time Savings (minutes) 7259 8,476

Bond Funding Cost
Adopted:
$7,876,000
Current Approved:
$21,187,000
Actual Expenditures:
$20,452,000

 

Status as of December 31, 2023.